How do you plan a backyard paver patio?

Dig for 4 to 6 inches of compacted crushed rock, 1 inch of sand and the paver thickness. Slope the surface about 1 inch per 4 feet away from the house, and order 5% extra pavers, or 10% if you have many cuts. That is Oregon State University Extension's method.

Last updated November 2026

How deep do you dig for a paver patio?

Add three layers together. Oregon State University Extension gives excavation depth as 4 to 6 inches of compacted crushed-rock base, plus 1 inch of sand bedding, plus the thickness of your paver [1].

Paver patio layers (OSU Extension)
LayerDepth
Compacted crushed-rock base4 to 6 in.
Sand bedding1 in.
PaverIts own thickness

Example only, with a made-up paver size: if your pavers were 2 inches thick, you would dig 7 to 9 inches. Read the real thickness off the paver spec sheet before you rent equipment. The deeper end of the base range costs more rock and labor; the source does not say when to use which, so ask your supplier about your soil.

Which way should a patio slope?

Away from the house, at about 1 inch for every 4 feet, per OSU Extension [1]. The slope moves rain off the surface and away from your foundation.

Worked example (our arithmetic): a patio that runs 12 feet out from the wall should drop about 3 inches from the house side to the far edge. A 16-foot patio drops about 4 inches. Set the slope in the base layer, not by thickening the sand.

Drop at 1 inch per 4 feet (our calculation)
Patio depth from houseTotal drop
8 ft2 in.
12 ft3 in.
16 ft4 in.
20 ft5 in.

How many extra pavers should you buy?

Order 5% more than the measured area. If the design has many cuts, order 10% extra [1]. Extra pavers from the same batch also give you matching spares for later repairs.

What tools does a DIY patio need?

The base is the part that has to be compacted, so a compaction tool matters most. A hand tamper suits small patios and edges. You will also want string lines, stakes and a level to set the slope.

How do you build it, step by step?

  1. Mark the outline with stakes and string. Check utilities before you dig.
  2. Set a string line for the slope: about 1 inch down per 4 feet from the house.
  3. Excavate to base depth plus 1 inch plus paver thickness.
  4. Spread and compact crushed rock in layers to 4 to 6 inches, following the slope.
  5. Screed 1 inch of bedding sand.
  6. Lay pavers, cut edges, and add an edge restraint.
  7. Compact the pavers and sweep joint sand in.

Backyard patio ideas that leave room for more

Our suggestions, based on the clearances on this site:

  • If you want a fire pit on the patio, it must sit at least 10 feet from the house, per the U.S. Fire Administration [2]. Make the patio deep enough, or put the pit on a separate gravel pad.
  • Keep a play area's 6-foot surfacing zone off the patio edge so hard pavers do not sit in the fall zone.
  • A small patio with a portable fire pit can move the fire to the lawn when needed.

Read more in our fire pit guide and playground guide.

Common mistakes

  • Using sand to fix low spots instead of correcting the base.
  • Sloping toward the house, or not sloping at all.
  • Skipping compaction between base layers.
  • Ordering the exact square footage and running short on cut pieces.
  • Building tight to the wall, then finding no safe spot for a fire pit.

Summary

  • Dig: 4 to 6 inches of base + 1 inch of sand + paver thickness.
  • Slope: about 1 inch per 4 feet, away from the house.
  • Order 5% extra pavers, 10% with many cuts.
  • Plan the 10-foot fire clearance before you size the patio.

Sources

  1. Oregon State University Extension, How to install pavers (undated)
  2. U.S. Fire Administration (FEMA), Outdoor fire safety (undated, accessed 2026-11)
BackyardIdeas.comis for sale by its owner, website included.For sale, website included
Buy now